Mason Hall Water Treatment

Project Title: Mason Hall, University of Birmingham.

Client: Briggs & Forrester MEP Ltd

Start Date : May 2008

Completion Date : September 2008

Price of Project : £77,944.00

Project Details

Chlorination to all new water services to B.S. 6700 2006 section 6, ref 6.1.10 and all applicable sub-sections. BSRIA Flushing as to BSRIA AG1/2001.

Commissioning of all building services with BTS.